ADDC

  • Start Date: 01 September 2013
  • End Date: 18 February 2016
  • Client: ADDC
  • Main Contractor: EMC Electromechanical Co LLC

“List of Activities for the mentioned Project:
1) Civil works – Excavation, backfilling, reinstatement works 2) Protection Works – Protection of existing services such as irrigation/drainage/water pipelines and relevant crossings. 3) Electrical Works – Installation of 11kV 3C x 300 sqmm CU cables in excavated trenches (direct buried) including cable dressing. 4) Carrying out 11kV 3C x 300sqmm CU cable jointing and termination works. 5) Testing and Commissioning of installed cables. 6) Supply, Installation testing and commssioning of Firbre Optic Cable panel.”

Other Projects

CONTRACT NO: D-101856

Equipping of Existing Substations and LV...

Read More
Equipping of Existing Substations and LV Distribution Network Expansion/Reinforcement Work in Eastern Region

RFX:4351300014, CE/0...

Installation Testing & Commissionin...

Read More
Installation Testing & Commissioning of Distribution SS & Kiosk and Disconnection Recovery Re-placement of Equipment.

DEWA CONTRACT RFX:4351300015, CE-0...

Installation of 11 KV Overhead on Wooden...

Read More
Installation of 11 KV Overhead on Wooden Poles & Dismantling & recovery of existing 33KV/ 11KV overhead lines.

Contract No ADDC Contract: D-120...

Load Transfer to new 132/11KV Primaries...

Read More
Load Transfer to new 132/11KV  Primaries E40 and W41 IN Abu Dhabi Island

CONTRACT NO: TRANSCO Contract: N-...

400kV Cabling Works between Sas Al Nakhe...

Read More
400kV Cabling Works between Sas Al Nakheel, Mahawi and Musaffah.