Duland Technical Services

  • Start Date: 01 August 2012
  • End Date: 01 September 2013
  • Client: Duland Technical Services
  • Main Contractor: EMC Electromechanical Co LLC

Laying of 11 KV 3C x 300 Sqmm XLPE Copper cable. Glanding & Termination 11 KV 1C x 185 Sqmm. Glanding & Termination 11 KV 3C x 300 Sqmm. Straight Joint of 3C x 11 KV , 300 Sq.mm XLPE cable. Glanding & Termination of 3C x 11 KV x 300mm^2 XLPE Cable. Glanding & Termination Works of 11 KV Cables 3C x 300Sq.mm & 3C x 185 Sq.mm. Recovery of 11 KV cables from existing Ducts 11 KV x 3C x 300/ 240/ 185mm2 cables. Re-rolling of recovered 11 KV x 3C x 300/240/185mm^2 on empty steel drums. Re-laying of recovered 11 KV x 3C x 300/240/185mm^2 cables.

Other Projects

CONTRACT NO: D-101856

Equipping of Existing Substations and LV...

Read More
Equipping of Existing Substations and LV Distribution Network Expansion/Reinforcement Work in Eastern Region

RFX:4351300014, CE/0...

Installation Testing & Commissionin...

Read More
Installation Testing & Commissioning of Distribution SS & Kiosk and Disconnection Recovery Re-placement of Equipment.

DEWA CONTRACT RFX:4351300015, CE-0...

Installation of 11 KV Overhead on Wooden...

Read More
Installation of 11 KV Overhead on Wooden Poles & Dismantling & recovery of existing 33KV/ 11KV overhead lines.

Contract No ADDC Contract: D-120...

Load Transfer to new 132/11KV Primaries...

Read More
Load Transfer to new 132/11KV  Primaries E40 and W41 IN Abu Dhabi Island

CONTRACT NO: TRANSCO Contract: N-...

400kV Cabling Works between Sas Al Nakhe...

Read More
400kV Cabling Works between Sas Al Nakheel, Mahawi and Musaffah.